Southeast Asian power systems and energy access
Indonesia's power sector, rural electrification and island grids, from village mini-grids to national regulation.
I have worked in Indonesia since 2017, first on rural electrification, then on rooftop PV and power sector studies. Much of my work elsewhere in the region has been funded by development banks and donors.
What I have worked on
- Remote and island grids. Many remote Indonesian islands rely on diesel generators. With colleagues at SERIS, I worked on how to size and introduce PV and batteries step by step in diesel-powered systems, including A diesel replacement strategy for off-grid systems based on progressive introduction of PV and batteries: An Indonesian case study (Applied Energy, 2018).
- A book on remote areas. With Professor Dipti Srinivasan, I edited Sustainable Energy Solutions for Remote Areas in the Tropics (Springer, 2020), in which practitioners describe solutions that have been applied in remote communities, their impacts, and how to make them last.
- Alva Energi. I co-founded Alva Energi in 2017. It has installed more than 800 kWp of solar PV across 18 cities and regencies in Indonesia.
- Regulation. I was one of three main authors of two studies for GIZ and Indonesia's Ministry of Energy and Mineral Resources, on ancillary services and on a regulatory framework and business model for battery energy storage systems. I have also worked with PLN on ancillary services, demand response and renewable energy forecasting.
- Feasibility studies in the region and beyond. At SERIS, I carried out feasibility studies for more than 7 GWp of PV and 1 GWh of battery storage. Studies I worked on were funded by ADB, the World Bank, the Inter-American Development Bank and USAID, in countries including the Philippines, Viet Nam, Sri Lanka, Mexico, Tuvalu and Suriname.
Questions this work helps answer
- How can an island grid move from diesel to PV and batteries without losing reliability?
- What does Indonesia's regulatory framework need for ancillary services and battery storage?
- What makes an energy access project last after the installers leave?
Publications on this topic
- Comparative Study of Ancillary Service as Recommendation for Ancillary Service Provision for IndonesiaGIZ Energy Programme Indonesia & ASEAN, in cooperation with the Directorate General of Electricity, Ministry of Energy and Mineral Resources
- 2024Optimal Design of a Hybrid Solar–Battery–Diesel System: A Case Study of Galapagos IslandsSolar 4(2), 232–245
- 2021Global sensitivity and uncertainty analysis of the levelised cost of storage (LCOS) for solar-PV-powered coolingApplied Energy 286, 116533
- 2021Novel forecast-based dispatch strategy optimization for PV hybrid systems in real timeEnergy 222, 119918
- 2020Life cycle cost analysis (LCCA) of PV-powered cooling systems with thermal energy and battery storage for off-grid applicationsApplied Energy 273, 115145
- 2020Sustainable Energy Solutions for Remote Areas in the TropicsSpringer, Green Energy and Technology series
- 2020Electrifying lives with community empowermentIECON 2020, 46th Annual Conference of the IEEE Industrial Electronics Society
- 2019Levelised Cost of Storage (LCOS) for solar-PV-powered cooling in the tropicsApplied Energy 242, 640–654
- 2018A multi-objective and robust optimization approach for sizing and placement of PV and batteries in off-grid systems fully operated by diesel generators: An Indonesian case studyEnergy 160, 410–429
- 2018
- 2017A siting and sizing optimization approach for PV–battery–diesel hybrid systemsIEEE Transactions on Industry Applications 54(3), 2637–2645
- 2017PHSO: A Graphic User Interface Optimizer for the Sizing Design of the PV Hybrid Systems33rd European Photovoltaic Solar Energy Conference and Exhibition (EU PVSEC)